The urban and rural water supply integration project in Huili County

The urban and rural water supply integration project in Huili County

Summary

The urban and rural water supply integration project in Huili County

Project Name: Huili County Urban and Rural Water Supply Integration Project
Project Address: Jingwei Reservoir, Shubao Township, Huili County, Liangshan City, Sichuan Province
Project purpose: Water supply for villages and towns
Main technical parameters of the pumping station
Main body dimensions: 18x9x1.3m
Unit configuration: 3 units (2 in use and 1 as backup)
Single-machine flow rate: 360m ³ /h
Head: 65m
Power: 110kW per unit, 380V
Control mode: The shore end is controlled by a control room
Connection method with the shore: Rocker arm connection to DN350 50 meters